Recently, the Democratic Republic of the Congo project team of China Railway Sixth Group Electrical Engineering Company successfully energized the 120kV power line expansion and reconstruction project for New Mining Industry, marking its official commissioning.
China Railway Sixth Group Electrical Engineering Company was mainly responsible for tower assembly, conductor fittings installation, and cable erection for the power line expansion and reconstruction project.
After the completion and commissioning of the line, the power supply capacity increased from 18 MW to 23 MW, significantly enhancing the mining area’s power supply capability and reliability. This provides strong electrical support for stable and increased production in the electrowinning workshop and holds great significance for promoting the development of New Mining.